HEDNO Communication regarding the application of l. 4951/2022 (GG 129/Α/04.07.2022) on the submission of applications for granting Final Connection Offers
As per Article 5, paragraph 4, of l.4951/2022 “Improving the Renewable Energy Sources licensing process– phase B, Licensing electricity production and storage, framework for the development of Pilot Sea Floating PV Stations and special provisions on energy and environmental protection”, applications on granting Final Connection Offers will be submitted online from the first up to the tenth day of each calendar month.
As part of the implementation of the above provisions, HEDNO is announcing that from 11.07.2022 to 31.07.2022 applications on granting Final Connection Offers for RES and CHP station will not be accepted, with the exception of disclosure applications ref. Article 38, submitted with a full folder, regarding the connection of RES and CHP stations to the Network which can be submitted throughout the current month.
From 01.08.2022 all connection applications for RES and CHP stations concerning mainland Greece and Interconnected Islands will be exclusively submitted on the online platform provided by the website of HEDNO together with all required documentation as this is specified in the respective law.
All relevant information and details on how to submit an application online will be uploaded on HEDNO’s website until the applications opening date.
More specifically, the opening date for submitting connection applications for RES and CHP stations covered by the provisions of article 132 of l. 4819/2021 will be specified with a new announcement.